Q1. A
set of cows can eat a crop in 20 days. However 10 cows did not go to
the crop. The remaining now can eat in 25 days. Find the original
number of cows
(a) 45 (b) 36
(c) 44 (d) 50
Q2. If 5 men or 10 women can do a job in 2 days, find how long 5 Men and 5 Women to do the same.
(a) 1.2 (b) 2
(c) 1.5 (d) 1.6
Q3. A
can do work in 3 days less than B, A works alone for 4 days and than B
takes over and completes it. If together 14 days were taken, how many
days would each take to complete the work?
(a) 11 and 14 (b) 8 and 11
(c) 15 and 18 (d) 12 and 15
Q4. A
and B have to make 600 machine parts, A worked for 2 hours and B for 5
Hours and they did half the entire work. They worked together for
another three hours and found that 1/20th of the work is yet to be
done. How much time does each take to do the whole work?
(a) 11 and 14 (b) 8 and 11
(c) 15 and 18 (d) 12 and 15
Q5. A
and B can mow the lawn in 6 hrs, B and C can mow the lawn in 8 hrs and
A and C can mow the lawn in 10 hrs. How long will it take the lawn if
all three work together?
(a) 5.3 (b) 5.1
(c) 5.2 (d) 5.6
Q6. A,
B, C are three typists who can type 216 pages in 4 hrs. in one hr C
types as many pages as B as B can type more than A. IN five hrs C can
type as many pages as A in seven hrs. How many pages does each type in
one hr.
(a) 15, 18, 21 (b) 16, 19, 22
(c) 12, 15, 18 (d) 18, 21, 24
Q7. 10
deer and 10 buffalos eat grass of 5 acres in a certain time. How many
acres will feed 20 deer and 10 buffalos for the same time, supposing a
buffalo eats as much as 2 deer?
(a) 7.5 (b) 6.67
(c) 7 (d) 6.95
Q8. A contractor undertook to do a certain work in 40 days and employed 60 men for it. In 15 days only 1/4th of the work was done. How many extra men should the contractor employ in order to complete the work in time?
(a) 48 (b) 50
(c) 40 (d) 42
Q9. A
and B can do a piece of work in 20 and 25 days respectively. They
started the work together and after some days A leaves the work and B
completes the remaining work in 13 days. After how many days did A
leave?
(a) 6.66 (b) 6
(c) 7.66 (d) 7
Q10. A
cistern can be filled by one pipe A in 10 minutes, by a second pipe B
in 25 minutes. It can be emptied by a waste pipe C in 10 minutes. In
what time will the cistern be filled if all the three were turned on at
once?
(a) 25 min (b) 20 min
(c) 12 min (d) 30 min
Q11. A
chemical plant has 4 tanks A, B, C and D, each containing 1000 litres
of a chemical. The chemical is being pumped from one tank to another as
follows:
From A to B @ 20 litres/minute
From C to A @ 90 litres/minute
From A to D @ 10 litres/minute
From C to D @ 50 litres/minute
From B to C @ 100 litres/minute
From D to B @ 110 litres/minute
Which tank gets emptied first and how long does it take in minutes to get empty after pumping starts?
(a) A, 16.66 (b) C, 20
(c) D, 20 (d) D, 25
Q12. In
nuts and bolts factory, one machine produces only nuts at the rate of
100 nuts per minute and needs to be cleaned for 5 minutes after
production of every 1000 nuts. Another machine produces only bolts at
the rate of 75 bolts per minute and needs to be cleaned for 10 minutes
after production of every 1500 bolts. If both machines start production
at the same time, what is the minimum duration required for producing
9000 pairs of nuts and bolts?
(a) 130 min (b) 135 min
(c) 170 min (d) 180 min
Q13. It
takes 6 technicians a total of 10 hours to build a new server from
direct computer, with each working at the same rate. If six technicians
start to build the server at 11:00 am and one technician per hour is
added beginning 5:00 pm at what time will the server be complete?
(a) 6:40 pm (b) 7:00 pm
(c) 7:20 pm (d) 8:00 pm
Q14. 3 small pumps and a large pump are filling a tank. Each of the three small pumps works at 2/3rd the
rate of the large pump. If all 4 pumps work at the same time, they
should fill the tank in what fraction of time that it would have taken
the large pump alone?
(a) 4/7 (b) 1/3
(c) 1/3 (d) 3/4
Q15. Three
friends’ asit, Arnold and afzal, work together to get all of these
chores done. The time it takes them to do the work together is six
hours less than asit would have taken working alone and half the time
afzal would have taken working alone. How long did it take them to do
these chores working together?
(a) 20 min (b) 30 min
(c) 40 min (d) 50 min
Q16. A
takes 4 days to do a work. B takes twice as long as B and D takes twice
as long as C. they are made in groups of two. One of the groups takes
two third of the time taken by the second pair. What is the combination
of the first pair?
(a) A, C (b) A, D
(c) B, C (d) B, D
Ans1. (d) Suppose number of cows = X
X can do the job in 20 days = 20X
Since 10 did not go, X – 10 could do the job in
25 days = (X – 10)25
Since job is same
20X = (X – 10)25
X = 50 cows
Ans2. (d) Here 5 men’s work = 10 women’s work
One man’s work = 5/10 = 1/2 women’s work
Therefore when it is 5 Men + 5 women
It is 5 men + 2.5 men = 7.5 men
Since 5 men can do the job in 2 days
1 man can do the job in 10 days
7.5 men can do the job in 12/7.5 = 1.6 days
Ans3. (d) Let B does the job in X days
Therefore A does the job in X – 3 days
As per problem 4/(X – 3) + 10/X = 1
Solving B’s days for job, X = 15, therefore A’s days = 15 – 3 = 12
Ans4. (d) Here suppose A does x machine parts per hour and B does y machine part per hour, therefore
2x + 5y = 300 and 3x + 3y = 270
Solving x = 50, so A can do in 12 hrs and y = 14, so y can do in 15 hrs
Ans5. (b) In one hour A and B can do 1/6th of lawn
In one hour B and C can do 1/8th of lawn
In one hour A and C can do 1/10th of lawn
Adding the three = 2(A + B + C)
= 47/120 = (47/240) th of job
Reciprocating 240/47 = 5.1 days
Ans6. (a) Let A types x pages per hour
B types y pages per hour
C types z pages per hour
As per question, 4x + 4y + 4z = 216
y – x = z
5z = 7x
Three equations three variables, solving
x = 15, y = 18, z = 21
Ans7. (b) Since buffalos eat twice than deer, then 1 buffalo’s work = 2 deer work
So for first job, 10 deer and 10 buffalos = 15 buffalos
And fore second job, 20 deer and 10 buffalos = 20 buffalos
If 15 buffalos can eat 5 acres in certain time, then in same time 20 buffalos will eat
20/15 × 5 = 6.67 acres
Ans8. (a) Work to be done in 40 days, as per schedule,
1/4th of
the work done in 15 days therefore the total work will be done in 60
days. Now mandays required for the entire job are 60 × 60 = 3600.
Mandays required for the left 3/4th of job = 3600 × ¾ = 2700
Mandays left with contractor
= 25 × 60 = 1500
Excess mandays required
= 2700 – 1500 = 1200
Here days cannot be extended therefore men required
= 1200/25 = 48 men
Ans9. (a) Suppose A worked for X days
A can do the job in 20 days, in one day 1/20th of the job, in X days = X/20th of job
B can do the job in 25 days, in one day 1/25th of the job, in X + 10 days = X + 13/24th of job
Now since the job is done
X/20 + (X + 13)/25 = 1
Solving X = 6.66 days
Ans10. (a) In one minute the amount of filing = 1/10 + 1/25
In one minute the mount of emptying = 1/10
Net effect = 1/10 + 1/25- 1/10 = 1/25, the cistern will fill in 25 minutes
Ans11. (c) Lets see the flow through the table below:
A B C D
– 20 + 20
+ 90 – 90
– 10 + 10
– 50 + 50
– 100 + 100
+ 110 – 110
Total + 60 + 30 – 40 – 50
D gets emptied first; it gets emptied in 20 minutes.
Ans12. (d) Time taken in producing 9000 nuts
= 9000/100 × 1 + 9000/1000 × 5
= 90 + 45 = 135 minutes
Time taken in producing 9000 bolts
= 9000/75 × 1 + 9000/1500 × 10
= 120 + 60 = 180 minutes
Thus for making 9000 pairs of nuts and bolts time taken is 180 minutes.
Ans13. (d) Time between 11 am to 5 pm = 6 hours
Now , 6 technicians take 10 hours to build a new server from direct computer.
Thus 1 technician takes 10 × 6 = 60 hours
i.e. in 1/60 of new server is built by 1 technician in an hour.
6 technicians work for 6 hours
Thus wok done by them = 36/60 = 3/5
Remaining work = 1 – 3/5 = 2/5
Now , 7 technicians work from 5 pm to 6 pm
Thus work done by them = 7/60
Again, 8 technicians work from 6 pm to 7 pm
Thus work done by them = 8/60
Again, 9 technicians work from 7 pm to 8 pm
Thus work done by them = 9/60
Thus total work done = 7/60 + 8/60 + 9/60
= 24/60 = 2/5
Hence, the server is built at 8 pm.
Ans14. (b) Let the rate of large pump be x units/hr
So rate of each small pump = 2x/3
When 4 pumps work at the same time, their combined rate = 3 × 2x/ 3 + x = 3x
Time taken = 1/3 of time taken be the large pump
Ans15. (c) 40 min
Ans16. (b) A’s 1 day’s work = ¼
By hypothesis,
B’s 1 day’s work = 1/8
C’s 1 day’s work = 1/16
D’s 1 day’s work = 1/32
Thus (A + D)’s 1 day’s work
= ¼ + 1/32 = 9/32
And (B + C)’s 1 day’s work
= 1/8 + 1/16 = 3/16
(B + C) can finish the work in 16/3 days
Thus (A + D) can finish the work in
= 32/9 days
= 2/3 × 16/3
= 2/3rd of time taken by B and C
This Topic Is Locked To Guest Posts
It's been a while since this topic was active, if you'd like to get it going again, please post as a registered member